Upgrading Mataki’Eua Well-field (Additional 15 wells one reservoir (4000 meter³)

  • Funded by: ADB/Aus.AID
  • Total cost: US$8.5 million
  • Status: Closed Bidding Date 21.3.15…Project Awarded ECECC
  • Completion date: June; 2016

Mataki’Eua Underground Electrical High Voltage

  • Funded by: TWB
  • Total cost: $400,000
  • Status: Completed
  • Completion date: Sept; 2015

Drilling one (1) borehole at ‘Ohonua

  • Funded by: TWB / GOVT
  • Total cost: $60,000
  • Status: Completed
  • Completion date: Sept; 2015

Drilling three (3) boreholes & installing booster pump at Vava’u

  • Funded by: TWB
  • Total cost: $103,000
  • Status: –
  • Completion date: Feb; 2016

Installing solar pump at Pangai Ha’apai

  • TWB
  • $37,000
  • Status: –
  • Completion date: Mar; 2016